The next round of 210 freeway closures are set for the next two weeks as construction crews continue removing the temporary falsework that has supported the bridge being built as part of the Gold Line extension to Azusa.
The schedule of closures is as follows:
Sunday-Thursday
9 p.m.: On-ramps start closing (Baldwin and Santa Anita Avenues)
Sunday, Monday and Tuesday
11 p.m.: Full closures begin; all lanes reopen by 5 a.m.
Wednesday and Thursday
Midnight: Full closures begin; all lanes reopen by 5 a.m.
These same closures are also scheduled for next week, Sunday through Thursday.